Construction Freight Requirements

What a jobsite delivery has to satisfy before the material is any good to the crew.

Specifications

Construction Delivery Requirements at a Glance

What a jobsite delivery has to satisfy before the material is any good to the crew.

RequirementThe specificationWhat it means for the load
Delivery windowA date set backward from the pour, the erection start or the inspection, often inside a city delivery curfew and a crane window measured in hoursThe pickup is scheduled from the site's window, and the driver calls ahead so the crane is not paid to wait on a gate
Offload methodCrane, telehandler or boom truck supplied by the site, rated on its load chart at the radius of the heaviest piece. No dock, no leveler, rarely a forkliftOffload equipment, piece weights and pick radius are confirmed before dispatch, and side loading equipment is assigned instead of a rear load box
Site accessPosted bridge limits, low clearances, turning radius on residential and downtown streets, gate hours, ground conditions after rainRoute checked to the gate, not to the zip code, and trailer length dropped or the load split when the last mile will not take a full length unit
DocumentationBill of lading carrying the job name and lot or phase, mill test reports on steel and rebar, bundle tags by mark number, submittal or approval referencesPaperwork travels with the load and the signed delivery receipt comes back with it, because a missing mill cert stops an inspection as hard as a missing bundle
Load sequenceSteel and precast shipped in erection sequence, rebar grouped by placing drawing, deck and board split by area or floorLoading order is written into the load plan, so first needed is last loaded and the crew is not cutting bands to hunt for mark numbers
Weather protectionGypsum board, insulation, bagged cement and finish lumber cannot get wet, and board that got wet is rejected even after it driesEnclosed equipment or full tarping specified at quoting, with the tarp type matched to the freight and dunnage that supports the full stack
SecurementFMCSA rules: two tiedowns past 5 feet of article length, two plus one more per additional 10 feet or fraction past 10 feet, aggregate working load limit at least half the cargo weight, blocking or chocking on round stockCoated and galvanized members get web straps, corner protectors and softeners instead of bare chain, and bundles are retensioned early in the run
OversizeLong steel, plank, tees and wide panels pass 8 feet 6 inches wide or run past the deck, and cross each state's threshold for flags, escorts and daylight only travelPermits, escorts and route planning handled at quoting so permit lead time sits inside the schedule instead of on top of it
Axle loadingRebar, plate, pipe and bagged cement load heavy in a short space, and a tandem is held to 34,000 pounds even when the load is far under 80,000 grossWeight distribution and axle position are planned off the piece list, and a spread axle or an added axle is assigned rather than forcing a legal gross onto one tandem

The equipment

The Trailer Is Chosen by the Piece and the Offload, Not by the Weight

One project runs through most of the deck types in the market. Rebar, pipe, lumber, trusses, roofing panels and structural steel ride flatbed, because they come off the side or overhead and nothing about them fits through a rear door. Anything tall enough to break the legal height on a flatbed steps down to a step deck, and plate girders, deep tees and heavy installed equipment go lower still on RGN or lowboy. Gypsum board, insulation, finish lumber and packaged goods run dry van, where weather is not a variable and a site with a forklift can unload without stripping tarps. A short heavy drop that will not fill a deck goes partial truckload rather than paying for air. Small deliveries to a site with no offload equipment at all take final mile with a liftgate. And when a piece is long enough, wide enough or tall enough to need permits, flags and escorts, it is oversized freight and it gets planned as oversized freight from the quote, not renamed at dispatch.

Ready to Ship?

Get a Free, No-Obligation Quote Today

A logistics specialist reviews your lanes and comes back with pricing and capacity. Support runs 24/7.

24/7 Support AvailableResponse in Under 10 MinutesNo Hidden Fees

Every carrier is vetted for operating authority and insurance, and we check the certificate before every dispatch, not once a year. USDOT 3411782 · MC 1100274